A second suite (the Code calls it a secondary suite) is legal in BC only once it has a building permit, passed inspections and, in most cities, a registration or occupancy sign-off. This guide covers the BC Building Code rules your drawings have to meet, what Surrey and six other cities ask for, which fees each city publishes, and who is allowed to draw the plans. Every fact links to the official page it came from.

On this page
  1. BC Building Code rules for a suite
  2. What second suite drawings must show
  3. Who can draw the plans
  4. Registered suite in Surrey
  5. Other cities compared
  6. Permit fees (published figures only)
  7. Step by step
  8. Vetting a designer
  9. Watch out for fakes and scams
  10. FAQ
  11. Sources

Short version: the province now allows a secondary suite or accessory dwelling unit in single-family zones across BC [2], but you still need a building permit from your city. Your plans must show the fire separation, smoke alarm layout, bedroom egress windows, ceiling heights and how heating and ventilation are kept separate, because those are the BC Building Code items the plan checker looks for [1]. In Surrey, a suite must also be declared and pays an annual Secondary Suite Service Fee of $893 [5].

BC Building Code rules for a secondary suite

Most houses with a suite fall under Part 9 of the BC Building Code 2024 (Division B). The table below lists the clauses that matter most for the drawings. We read each clause in the Province’s 2024 Code text on November 4, 2026 [1]. Your city can tell you if a later revision applies to your application date.

TopicWhat the Code saysClause
Fire separation between unitsAt least 15 min if every smoke alarm in the house is photo-electric and interconnected; 30 min if an extra interconnected photo-electric alarm is added in each unit and common space; 45 min if neither; no rating needed if the house is sprinklered9.10.9.16.(4); 9.10.19.5.(2)
Assemblies that meet 15 and 30 minPrescriptive constructions are listed so you don’t need a tested assembly9.10.3.1.(2) and (3)
Bedroom egressEach bedroom needs a window or exterior door openable from inside without tools, with an unobstructed opening of at least 0.35 m² and no dimension under 380 mm; 760 mm clear in front if it opens into a window well (not required if the suite is sprinklered)9.9.10.1.
Shared exitsRules for an exit shared by both units9.9.9.3.
Ceiling height2.1 m over the required areas of living, dining, kitchen and bedroom spaces (new work)Table 9.5.3.1.
Ceiling height, existing houseFor a suite added to an existing house, the alternative is not less than 1.95 m, and 1.85 m under beams and ductsDivision A, Table 1.1.1.1.(6)
SoundEach unit separated by the listed construction (insulated joist and stud spaces, resilient channel one side, 12.7 mm gypsum), or STC 43, or ASTC 409.11.1.1.(2)
Ducts and heatingOne unit’s duct system must not connect directly to the rest of the house unless it’s built to stop smoke circulation and has fire dampers9.33.1.1.(3); 9.32.3.2.(4) and (5)
Fire separation doorsA self-closing device is required on doors in a required fire separation9.10.13.10.

The existing-house alternatives in Division A apply only to a suite added to a house that already exists. A new house built with a suite must meet the full Division B numbers [1]. Kelowna’s 2026 suite bulletin turns these rules into a chart. A 30 min separation uses insulated joists and studs, resilient channel and 12.7 mm gypsum, plus an extra interconnected alarm in each unit. A 45 min separation uses Type X gypsum assemblies and doesn’t need the alarms linked to the main house [15]. It’s a handy reference even outside Kelowna, but your own city’s plan checker has the final say.

What second suite drawings must show

Each city publishes its own checklist, but the published lists overlap heavily. Here is what the official checklists we read ask for:

Saanich asks for plans at a normal drafting scale such as 1/4″ = 1′, and one energized EV outlet for each new dwelling unit [20]. In Nanaimo, every plan set must show the designer’s name and address (Building Bylaw 7224, s.8.5), and the City publishes a Plan Requirement Checklist [11][12].

Who can draw the plans

None of the city suite pages we read requires a particular kind of professional for a simple suite in a house. Saanich tells owners to consult a builder, building designer or architect [19]. In practice, three kinds of people draw suite plans:

WhoWhen they fitWhere to check them
Building or residential designerTypical Part 9 suite in a house.ASTTBC directory [25]; BCABD member directory [26]
Structural engineer (P.Eng.)When a wall comes out and beams or point loads change, or when the city asks for sealed structural work and Letters of Assurance [28]EGBC registrant directory [24]
ArchitectUsually not needed for a house suite. AIBC explains which buildings require one [22].AIBC online directory [23]

About “BCIBD”: we found no current BC body by that name. The BCABD’s own history says the designers’ group became the Building Designers Institute of BC under ASTTBC, and that the BC Association of Building Designers (BCABD) formed in 2020 [27]. To check a designer, search the ASTTBC and BCABD directories. Membership is voluntary, so a designer who isn’t listed isn’t automatically a bad choice. Still, ask them why they aren’t listed.

How to get a registered suite in Surrey

Surrey treats a suite as a dwelling unit inside a house whose habitable area is no more than 40% of the principal unit, and the suite can’t be a separate strata lot [4]. One suite is allowed per single-family, semi-detached or duplex unit. Suites aren’t allowed in a coach house or garden suite. Land Use Contracts and Building Schemes on title can still prohibit a suite, so check your title first [4]. If your house was built with a “Suite Ready” permit, ask the City, because that can shorten the work [4].

What you submit

The Secondary Suite Permit page lists these items [3]:

You can submit by email following the City’s digital submission guide, or in person. Keep the approved drawings on site for inspections [3].

Registration and the suite fee

All Surrey suites must be registered using the Secondary Suite Declaration Form. The City bills $1,000 for each unregistered suite [5]. A registered suite pays an annual Secondary Suite Service Fee of $893 per suite. Garbage, recycling and organics service costs $172.04 for one suite and $340.00 for two or more [5]. Surrey says a suite is automatically registered on your property taxes [4]. You can check a property with the City’s Secondary Suite Fee Web Inquiry tool [4].

Permit fees in Surrey

Surrey collects a non-refundable flat fee, based on the cost of work, when your plans are reviewed. The balance is due before the permit is issued [3]. Under Building Bylaw No. 17850, the first payment depends on the declared value [6]:

Declared value of workInitial non-refundable payment
$0 to $19,999$50
$20,000 to $99,999$150
$100,000 to $999,999$700
$1M to $4,999,999$5,500
$5M and over$25,000

The full permit fee comes from the City’s fee schedule and estimator [6]. Questions: zoning 604-591-4448, client services 604-591-4086 [4]. For Surrey permits in general, see our Surrey building permit guide.

Other cities compared

CityKey rules on the city’s own pageOfficial page
VancouverA suite has its own kitchen, living area and separate outside access. No strata title and no third suite; a duplex may have one suite per unit. You need a development and building permit, an Owner’s Undertaking Letter and plans. The suite isn’t legal until the final inspection passes. Renting it long-term needs a business licence.Creating a secondary suite [7]
VictoriaA suite is legal once all required building, plumbing and electrical permits are issued, the work is inspected, and a final Occupancy Permit is issued.What can I do with my property? [8]
NanaimoA Secondary Suite Permit is required. Plans follow the City’s Plan Requirement Checklist, and the designer’s name and address must be on every plan.Secondary Suite Permit [10][11][12]
KelownaThe suite is at most 90 m² and must be on community water. Required: a parking stall, a lit hard-surfaced path at least 860 mm wide, a visible suite address, hardwired interconnected smoke and CO alarms, local heat control and one cooled room. Submit two scaled drawing sets and a title search dated within 30 days.Secondary suite requirements [14][15][16]
BurnabySuites are allowed in the R1, A1, A2, A3 and RM6 zones and need building and subtrade permits plus inspections. File a Supplementary Utility Fees Declaration within 30 days of a change. Renting an unregistered suite can bring a $1,000 fine.Secondary Suite Program [17]
AbbotsfordSuites must be registered. Registration confirms the suite meets the BC Building Code and the Zoning Bylaw. Owners of unauthorized suites may be fined $500 per day.Secondary Suites [18]
SaanichSuites are allowed in all RS, RD and A zones, one per primary dwelling, wholly inside the house. Each suite needs an extra parking space with a Level 2 EV outlet and an Occupancy Permit.Secondary Suites [19][20]
LangfordThe City’s page lists one suite per dwelling, municipal sewer, an extra parking space and owner occupancy, and says a covenant against strata titling must be registered. Owner occupancy may have changed under the provincial housing rules, so confirm with the City at 250-478-7882.Planning and Zoning [21]

City guides: Vancouver suites · Victoria suites · Nanaimo suites · Kelowna permits · Burnaby permits · Abbotsford permits · Saanich permits · Langford permits · Duncan suites.

Permit fees: only what cities publish

These are the suite-related figures on each city’s own page, checked November 4, 2026. We don’t give typical totals, because the building permit fee usually depends on the value of the work.

CityPublished figuresBuilding permit fee
SurreyInitial payment $50 to $25,000 by value; Secondary Suite Service Fee $893 per year; unregistered suite billed $1,000 [5][6]Fee schedule and estimator [6]
VancouverOptional special inspection for legalizing: $282 + GST [7]Not stated on the suite page
VictoriaNone on the suite pageCity fee guide [9]
NanaimoNone on the suite pageCity fee calculator [13]
KelownaA $300 sewer development fee may apply where the house is on City sewer [15]Not stated on the suite page
BurnabyPossible $1,000 fine for an unregistered rented suite [17]Not stated on the suite page
Abbotsford$100 application fee (credited to the permit); $260 new registration fee; $270 annual infrastructure fee [18]Fees and Charges Bylaw, Schedule G [18]
Saanich, LangfordNone on the suite pagesAsk the municipality

Design fees aren’t published by the cities, and we didn’t find a reliable public figure, so we don’t quote one. Get written quotes for the same scope from two or three designers.

Step by step

  1. Check zoning and title. Confirm a suite is allowed on your lot and that no covenant, Land Use Contract or Building Scheme forbids it [4].
  2. Measure what you have. Measure ceiling heights, bedroom windows and the exit path, then compare them with the Code table above [1].
  3. Choose a separation strategy. Pick 15, 30 or 45 min, or sprinklers. That choice sets your alarm wiring [1].
  4. Hire someone to draw it, and an engineer if beams or walls change.
  5. Apply with the city’s form, title search and plans. Pay the initial fee [3][18].
  6. Answer plan-review questions and pay the balance when the permit is issued [3][18].
  7. Build and book inspections, with the approved drawings on site [3].
  8. Get final sign-off: occupancy, a final inspection or registration, depending on the city [7][8][18][19].
  9. Register and license it: Surrey suite declaration, Burnaby utility declaration, Vancouver business licence [5][7][17].

Vetting a designer

Watch out for fakes and scams

See also: who draws permit plans in Nanaimo and how to submit permit drawings in BC.

Frequently asked questions

Do I need drawings for a second suite in BC?

Yes. Every city in this guide asks for plans with a suite permit application. Surrey asks for site and floor plans; Kelowna asks for two scaled sets with sections and elevations.

What fire separation does a secondary suite need?

Under BC Building Code 9.10.9.16.(4): 15 minutes if every smoke alarm is photo-electric and interconnected, 30 minutes with an extra interconnected alarm in each unit, 45 minutes otherwise, or none if the house is sprinklered.

What is the minimum ceiling height in a basement suite?

2.1 m for the main rooms under Table 9.5.3.1. For a suite added to an existing house, Division A Table 1.1.1.1.(6) allows 1.95 m, and 1.85 m under beams and ducts.

How do I get a registered suite in Surrey?

Get a building permit with Surrey’s application form, a title search and plans, pass inspections, then file the Secondary Suite Declaration Form. Registered suites pay an $893 annual Secondary Suite Service Fee.

Do I need an architect or engineer for a secondary suite?

Usually not an architect for a house suite. An engineer is needed when structure changes, such as removing a bearing wall, or when the city asks for sealed drawings. A building designer usually draws the rest.

Is BCIBD the body that licenses building designers?

We found no current body by that name. Designers can join ASTTBC or the BC Association of Building Designers (BCABD), and both have public directories. Membership is voluntary.

How much does a second suite permit cost?

It depends on the city and the value of the work. Surrey’s first payment ranges from $50 to $25,000 by value. Abbotsford charges a $100 application fee plus a $260 registration fee. Other cities set the fee after you apply.

Sources

All pages checked November 4, 2026.

  1. BC Building Code 2024 (Province of BC)
  2. Small-Scale Multi-Unit Housing (Province of BC)
  3. Secondary Suite Permit (City of Surrey)
  4. Building or legalizing a secondary suite (City of Surrey)
  5. Secondary suites bylaw and fees (City of Surrey)
  6. Building permit fees and fee estimator (City of Surrey)
  7. Creating a secondary suite (City of Vancouver)
  8. What can I do with my property? (City of Victoria)
  9. Guide to building permit fees and deposits (City of Victoria)
  10. Secondary Suite Permit (City of Nanaimo)
  11. Plan Requirement Checklist (City of Nanaimo, PDF)
  12. Building Bylaw 7224 (City of Nanaimo, PDF)
  13. Permit fee calculator (City of Nanaimo)
  14. Secondary suite requirements (City of Kelowna)
  15. Bulletin 26-01: Secondary Suite (City of Kelowna, PDF)
  16. Checklist: Building Permit, Secondary Suite (City of Kelowna, PDF)
  17. Secondary Suite Program (City of Burnaby)
  18. Secondary Suites (City of Abbotsford)
  19. Secondary Suites (District of Saanich)
  20. Residential Building Permit: Renovation checklist (District of Saanich, PDF)
  21. Planning and Zoning: Secondary suites (City of Langford)
  22. Does your project need an architect? (AIBC)
  23. AIBC online directory
  24. EGBC registrant directory
  25. ASTTBC registrant directory
  26. BCABD member directory
  27. History of residential and building designers in BC (BCABD)
  28. Letters of Assurance (Province of BC)
  29. Licensed builder registry (BC Housing)
  30. Get a clearance letter (WorkSafeBC)
  31. Home repair contractors (Clicklaw Wikibooks)

Related: Secondary suite permits in BC · Surrey building permits · Vancouver building permits · Victoria building permits · Nanaimo building permits