Permit Guide · Vancouver Island

Oak Bay building permits: fees, suites, decks and sheds

The District of Oak Bay issues building permits for work in Oak Bay. You apply by email, the fee is based on the value of the work, and you pay a review fee before staff look at your plans.

Nearby: Victoria · Vancouver Island region · all permit guides

Not sure your job needs a permit at all? See do I need a building permit for this?

On this page
  1. Permit fees
  2. How to apply
  3. Decks, sheds and fences
  4. Secondary suites
  5. Who to contact

Permit fees

Fees come from Planning, Building and Development Fees and Charges Bylaw No. 4845, 2023 (PDF):

Under Building and Plumbing Bylaw 4247 (PDF), 20% of the permit fee is paid when you apply. It is a non-refundable application review fee, and it is credited against the total if the permit is issued. Other rules in the same bylaw:

Worked example: a $60,000 deck and renovation is $150 + 1.3% × $60,000 = $930. The review fee due at application is 20% of that, or $186. Other charges can be added when the final fee is due, such as tree permits, engineering permits, development cost charges, damage deposits and other securities. Amenity contribution and development cost charges apply only to new housing units beyond what already existed.

How to apply

  1. Get the Building Permit Application form online or at Municipal Hall, 2167 Oak Bay Ave.
  2. Email the form, plans and supporting documents to inspections@oakbay.ca. The form’s checklist asks for:
    • A title certificate no more than 30 days old, plus legal notations (covenants, rights-of-way).
    • An agent consent form if you are not the owner, and strata approval where it applies.
    • Letters of assurance where they are required.
    • Drawings at 1/4″ = 1 ft: elevations, floor plans with room uses, a site plan, a cross-section and project data, in digital format with a maximum of 8 MB.
  3. Ask Parks at 250-592-7275 whether you need a tree management plan; most applications do. If one is required, protective tree fencing must go up before the permit is issued.
  4. Staff send an invoice for the application fee. The review starts only after it is paid; the District says to allow several weeks.
  5. Pay the balance, then book the mandatory inspections as you build.

In the Uplands, exterior work must also pass the Uplands Design Guidelines before a permit is issued.

Decks, sheds and fences

Work that doesn’t need a permit must still meet municipal bylaws and the BC Building Code (District of Oak Bay: Building Permits).

Secondary suites

Building a new suite, or legalizing one built without approval, needs a building permit. The District’s rules:

Apply with an Owner Declaration of Secondary Suite form. A suite is legal only when its building, plumbing and electrical permits are approved, the inspections are passed, and Oak Bay issues an occupancy permit (District of Oak Bay: Secondary Suites).

Who to contact

Building inspections: inspections@oakbay.ca, 250-598-2042 ext. 7496. Inspectors take counter questions at Municipal Hall (2167 Oak Bay Ave.) Monday to Friday, 8:30 to 10:00 am. Electrical and gas permits come from Technical Safety BC.

Watch out: paying utility charges or renting out a suite does not make it legal; only the occupancy permit does. If work starts before the permit is issued, Oak Bay doubles the permit fee.

We could not confirm these on an official page, so we left them out: fence permit rules, fees specific to suites, and current review times.

Sources and official links

This page relies on the official pages below. Rules, fees and processes change, so check the authority before you apply or spend money.

Links checked November 1, 2026. Found an error or a broken link? Report it.