The District of Squamish charges a flat rate per $1,000 of value plus a tiered processing fee, and it has firm rules on servicing and timing. Here is what the April 2026 fee bylaw says and how the process runs.
Inside the District of Squamish, building permits are issued by the District’s building department. Properties outside the District, in the surrounding electoral areas, fall under the Squamish-Lillooet Regional District (SLRD). Fees here come from the District’s Fees and Charges Bylaw No. 3185, 2025, in the consolidation dated April 2026.
The District’s FAQ says a shed of 10 m² (107 ft²) or less does not need a building permit, and a deck 0.6 m (2 ft) or more above grade does. New buildings, additions, structural alterations, plumbing and demolition all need permits. Zoning still applies to exempt structures.
Is my project allowed? Zoning decides setbacks, height, lot coverage and whether a suite is allowed. Read your zone in Zoning Bylaw No. 2200 before you draw or apply.
Checked November 1, 2026 (District of Squamish): OCP and Zoning Bylaw document centre (Zoning Bylaw 2200, consolidated September 2026)
Worked example: a $150,000 residential project at the standard rate is 150 × $11 = $1,650. Because the value is over $100,000, the schedule also lists a $500 processing fee. The bylaw does not say plainly whether that fee is credited against the permit fee, so confirm with the District. Fees paid at issuance can also include development cost charges, deposits and lot grading charges. Compare cities in the BC permit fee estimator.
Starting without a permit adds a 150% surcharge, with a $1,000 minimum. If no work has started, 75% of the permit fee is refundable.
For current wait times, the District asks you to call 604-815-6872.
A note on drafters: the District’s fees cover review only. Your designer bills separately for drawings and changes; there is no official published rate, so get a written quote that covers revisions.
Book inspections by phone, Monday to Friday, 10:30 am to 2:30 pm. The FAQ warns of waits of up to 5 business days, so book early. A permit expires if work does not start within 6 months or stops for 180 days. Extensions are charged at 25%, 50% or 100% under the fee bylaw.
District of Squamish building department · building@squamish.ca · 604-815-6872. Engineering questions: 604-815-5012. Electrical and gas permits come from Technical Safety BC.
This page relies on the official pages below. Rules, fees and processes change, so check the authority before you apply or spend money.
Links checked November 1, 2026. Found an error or a broken link? Report it.