What each BC city officially publishes about how long a building permit takes, with the date and the source link. Where a city publishes nothing, we say so.
Last updated: September 2026. Figures were read from each city’s own page on September 25, 2026 (Chilliwack on September 28, 2026) and are refreshed monthly. Cities measure different things (median, average, queue date or target), so do not compare numbers across cities as if they were the same measure. Your own permit can take longer if the application is incomplete or needs revisions.
This page replaces our earlier Vancouver Island wait-times page. It now covers 10 BC municipalities that publish some official processing time, queue or target, and lists 13 more whose permit pages publish nothing we could find. Every figure below is copied from the city’s own page with its date and link. We do not estimate times for cities that publish nothing.
| City | Region | What is published | As of | Link |
|---|---|---|---|---|
| Vancouver | Metro Vancouver | Median elapsed time, permits issued in the month | August 2026 (monthly figures) | source |
| Surrey | Metro Vancouver | Average of the last 30 days (building permits) vs. City target | Last updated October 5, 2026 | source |
| Abbotsford | Fraser Valley | Queue: plans now being reviewed were submitted before this date (applications waiting) | Last updated September 24, 2026 | source |
| Chilliwack | Fraser Valley | Queue: residential permits now being reviewed have this application date | Read September 28, 2026 (the page shows no update date) | source |
| Nanaimo | Vancouver Island | Queue: applications waiting and the filing date of the next file up for review | Live list, read September 25, 2026 | source |
| Burnaby | Metro Vancouver | Average review time (news release) and pre-application review time | News release August 26, 2026; pre-application figure undated on the page | source |
| City of North Vancouver | Metro Vancouver | Average processing time, complete application to decision | Undated on the page (read September 25, 2026) | source |
| West Kelowna | Okanagan | Target timelines (business days, complete applications) | Undated targets (read September 25, 2026) | source |
| Penticton | Okanagan | Estimated turnaround to first plan review or issuance (complete applications) | Undated PDF (file properties show 2016) | source |
| Coquitlam | Metro Vancouver | Service standard for pre-screening only | Undated (read September 25, 2026) | source |
What it measures: Median elapsed time, permits issued in the month. As of: August 2026 (monthly figures). Source: City of Vancouver: build a new house or laneway house (permit processing times) · Vancouver permit guide
| Permit type | Published figure |
|---|---|
| New build, low-density housing | 20.0 weeks (60 permits) |
| Standalone laneway house | 15.6 weeks (10 permits) |
| Residential renovation, lower complexity | about 3.4 weeks (median 23.5 days, 68 permits) |
| Commercial / mixed-use renovation, lower complexity | 3.0 weeks (21 days, 71 permits) |
The City’s pages show these medians from its Open Data “issued building permits” dataset. We ran the same query the page uses; elapsed time runs from when the permit number is created to issuance, weekends included.
What it measures: Average of the last 30 days (building permits) vs. City target. As of: Last updated October 5, 2026 (we checked it October 9, 2026). Source: City of Surrey: permitting timelines · Surrey permit guide
| Permit type | Published figure |
|---|---|
| Residential building permit | 4.5 weeks (target 10 weeks) |
| Residential addition and renovation | 3 weeks (target 6 weeks) |
| New tenant improvement | 4.1 weeks (target 10 weeks) |
| Minor tenant improvement | 1 day (target 3 business days) |
| Medical clinic tenant improvement | 1.7 weeks (target 3 weeks) |
| Residential rezoning (6-month average) | 12.9 weeks (target 12 weeks) |
| Multi-family / commercial / industrial rezoning (6-month average) | 9.6 weeks (target 16 weeks, plus 4 with an ADP) |
What it measures: Queue: plans now being reviewed were submitted before this date (applications waiting). As of: Last updated September 24, 2026. Source: City of Abbotsford: permit wait times · Abbotsford permit guide
| Permit type | Published figure |
|---|---|
| New / addition, residential homes | Jun 30, 2026 (75 waiting) |
| Residential renovations | Jul 19, 2026 (32 waiting) |
| Agricultural | Jul 10, 2026 (16 waiting) |
| New / addition, ICI and multifamily | Jul 16, 2026 (14 waiting) |
| Tenant improvements | Aug 14, 2026 (13 waiting) |
| Signs | Sep 21, 2026 (0 waiting) |
150 applications in total were waiting for plan review. On the day we read it, new homes submitted on Jun 30 were being reviewed, which is roughly 12 weeks of queue.
What it measures: Queue: residential permits now being reviewed have this application date. As of: Read September 28, 2026 (the page shows no update date). Source: City of Chilliwack: turnaround times
| Permit type | Published figure |
|---|---|
| Residential building permits (excluding multifamily) | Application date August 25, 2026 |
On the day we read it, residential files were being reviewed about 5 weeks after they were submitted. Multifamily applications are not included.
What it measures: Queue: applications waiting and the filing date of the next file up for review. As of: Live list, read September 25, 2026. Source: City of Nanaimo: pending building permits · Nanaimo permit guide
| Permit type | Published figure |
|---|---|
| Single-family residential | 6 waiting; next file filed Aug 17, 2026 |
| Commercial | 3 waiting; next file filed Dec 22, 2025 |
| Commercial alteration | 2 waiting; next file filed Aug 24, 2026 |
| Leasehold | 1 waiting; next file filed Aug 13, 2026 |
| Demolition and sign | 0 waiting |
Nanaimo notes staff cannot give specific dates for individual files. A next-up date of Aug 17 on Sep 25 means single-family files were waiting about 5–6 weeks for first review.
What it measures: Average review time (news release) and pre-application review time. As of: News release August 26, 2026; pre-application figure undated on the page. Source: City of Burnaby news release, Aug 26, 2026 · Burnaby permit guide
| Permit type | Published figure |
|---|---|
| Residential building permit review (average) | 13 days, down from 21 days |
| New home pre-application review (complete submissions) | about 15 business days |
The 13-day figure is a review time from a City news release, not a live dashboard. The pre-application figure is on the City’s new home construction page.
What it measures: Average processing time, complete application to decision. As of: Undated on the page (read September 25, 2026). Source: City of North Vancouver: permits and inspections
| Permit type | Published figure |
|---|---|
| Home improvement | 4 to 5 months |
| New construction | 11 to 12 months |
| Business space renovation | 6 months |
The City says the figures vary by project complexity.
What it measures: Target timelines (business days, complete applications). As of: Undated targets (read September 25, 2026). Source: City of West Kelowna: building permits and inspections
| Permit type | Published figure |
|---|---|
| Housing Incentive Program projects | 5 days |
| Residential small project (decks, pools, retaining walls) | 10 days |
| Single-family dwelling or duplex | 15 days |
| Residential multifamily | 1 month |
| Commercial small project | 15 days |
| Commercial or industrial new project | 1 month |
These are targets, not measured results. Development permits are usually processed first and can add time.
What it measures: Estimated turnaround to first plan review or issuance (complete applications). As of: Undated PDF (file properties show 2016). Source: City of Penticton: estimated permit review times (PDF)
| Permit type | Published figure |
|---|---|
| Simple permits (plumbing with trade ticket, crane, HVAC) | 1–5 business days |
| Accessory buildings, decks, interior renovations | 14 business days |
| New single and two-family homes, major additions | 21 business days |
| New buildings or major renovations with multi-department review | 30 business days |
The document is old and says the times are not a guarantee. Confirm with the building file manager.
What it measures: Service standard for pre-screening only. As of: Undated (read September 25, 2026). Source: City of Coquitlam: permit application review · Coquitlam permit guide
| Permit type | Published figure |
|---|---|
| Preliminary application pre-screen | 3–5 business days |
This is only the completeness check. Coquitlam does not publish a total processing time on this page.
For these places we checked the building permit pages linked below on September 25, 2026 and found no published processing time, queue or target. That does not mean permits are slow or fast, only that the city does not post a number. Ask the building department for a current estimate when you apply.
| Municipality | Region | Status | Permits page |
|---|---|---|---|
| Victoria | Vancouver Island | Not published | permits page · our guide |
| Saanich | Vancouver Island | Not published | permits page · our guide |
| Langford | Vancouver Island | Not published | permits page · our guide |
| Duncan | Vancouver Island | Not published | permits page · our guide |
| Cowichan Valley Regional District | Vancouver Island | Not published | permits page · our guide |
| Courtenay | Vancouver Island | Not published | permits page |
| Richmond | Metro Vancouver | Not published | permits page · our guide |
| District of North Vancouver | Metro Vancouver | Not published | permits page |
| City of Langley | Metro Vancouver | Not published | permits page · our guide |
| Township of Langley | Metro Vancouver | No current figures published; a March 14, 2025 news release cited an average of about two weeks for smaller permit types | permits page · our guide |
| New Westminster | Metro Vancouver | Not published | permits page · our guide |
| Maple Ridge | Metro Vancouver | Not published | permits page |
| White Rock | Metro Vancouver | Not published | permits page · our guide |
| Kelowna | Okanagan | Not published | permits page · our guide |
| Kamloops | Thompson-Nicola | Not published | permits page · our guide |
| Prince George | Northern BC | Not published | permits page |
Missing a city that publishes times? Tell us and we will add it at the next monthly update.
Related: 30-second permit quiz · BC permit fee estimator · deck permit how-to · secondary suite how-to
It depends on the city and the project. Among cities that publish figures, Surrey reported 4.5 weeks for residential building permits (target 10, as of October 5, 2026), Vancouver a median of 20 weeks for new low-density homes issued in August 2026, and Abbotsford was reviewing new-home plans submitted about 12 weeks earlier. Check the table for your city and its date.
Each city measures something different: Vancouver publishes medians, Surrey and Burnaby averages, Abbotsford and Nanaimo queue dates, and West Kelowna and Penticton targets. A queue date for first review is not the same as total time to issuance.
Ask the building department for a current estimate when you apply, and submit a complete application. Incomplete applications are the most common cause of delay.
Monthly. The last update was September 2026. Some city pages (Nanaimo, Abbotsford, Surrey) change more often than that, so follow the source link for the live figure.
It was folded into this provincial page. The old address redirects here, and the Island cities (Nanaimo, Victoria, Saanich, Langford, Duncan, CVRD, Courtenay) are all still listed.
Independent information only. This guide is a planning aid, not legal, engineering or building-code advice. Codes and bylaws change, and the building official for your address has the final say. Confirm every requirement before you design, apply or dig.
This guide relies on the official pages below. Rules, fees and processes change, so check the authority before you apply or spend money.
Links checked September 28, 2026. Found an error or a broken link? Report it.